Good morning / afternoon everyone. Thank you for joining.
Today I want to walk us through where we are with the emissions regulation compliance work, what went wrong in the past, and where we need to focus going forward.
Let me start with the R101 case from 2020.
In 2020, we had a compliance issue with the R101 model. This is one of our reference cases for what happens when our process has gaps.
After R101, IRCO โ our internal regulatory coordination office โ created what's called an organization charge. They used EPS to visualize where the problems were.
The key learning: the issue wasn't only with the spare parts. It was also with the wider process. So IRCO's charge to us was: identify where our current process breaks down, then close the gaps.
Let me walk you through what our work flow looks like today:
Using the EPS approach, I have identified eight problems in our current process:
- Guidance on the standards โ what they actually mean in our context
- Clarification on Route 3 โ why we're using it and how
- Support on check sheet design โ how to structure it model-by-model
- Final submission process โ who owns the final sign-off (DMC vs. other)
- Timeline โ when we need each deliverable
In return, we will:
- Develop a model-specific check sheet (one per model: gasoline, diesel, hybrid, ICE)
- Use EPS to visualize and validate the process
- Submit a clean final report to the correct authority
- Update our organizational charge document to reflect the new flow
| When | Action | Owner |
|---|---|---|
| This week | EMC reviews our 8-problem analysis, provides written guidance on items 1, 4, 5 | EMC |
| Next week | Joint workshop: redesign check sheet template (model-by-model) | EMC + ASSB designer |
| Within 2 weeks | Pilot run on R101 to validate new flow | ASSB team |
| Monthly | Status update at PMM using EPS visualization | PMM coordinator |
The good news: the EPS approach worked for R101 โ it just needs to be applied systematically for our other regulation items.
My ask: Let's commit to closing at least 3 of the 8 problems by next PMM.
Thank you. Questions?
| Term | Meaning |
|---|---|
| EMC | External Manufacturing Compliance |
| DMC | Department of Motor Compliance |
| PMM | Plant Monthly Meeting |
| EPS | Toyota's visualization / analysis tool (used to map problems) |
| COP | Confirmity of Product (product conformance record) |
| TPS | Toyota Production System |
| Office TPS | Office Toyota Production System (administrative/office application of TPS) |
| IRCO | Internal Regulatory Coordination Office |
| R101 | Specific compliance case from 2020 (reference) |
| 35 regulation items | Approved items at PMM (scope) |
| Route 3 | One of the 3 process flows being used (needs clarification) |
- Total runtime: ~9 minutes
- Tone: Professional Toyota-formal
- Pace: Slow at the 8-problem section (let it sink in)
- Engagement: Ask for "thumbs up if Problem 1 resonates" after the first 2 problems
- Backup slides: Have the EPS visualization on screen to point at